Demurrage, Laytime, and Despatch: Key Terms Explained

Updated: Apr 10

Every day, port delays cost the global shipping industry over $1 million. These bottlenecks affect supply chains, leading to missed deadlines and strained contracts. At the core of these challenges are three crucial concepts: demurrage, laytime, and despatch. Understanding these is not just about compliance—it's about optimizing operations and safeguarding profits.


Cargo ships being loaded at a busy port, with towering cranes and vibrant shipping containers creating a dynamic scene under a clear blue sky.
Cargo ships being loaded at a busy port, with towering cranes and vibrant shipping containers creating a dynamic scene under a clear blue sky.

Voyage agreements rely on precise timelines. For instance, a ship's "laytime" starts only after the ship's Master submits a formal & valid Notice of Readiness (NOR). Courts, as seen in the landmark case The Tres Flores, have upheld this notice as valid even if cargo is not immediately accessible. Exceeding pre-agreed loading or unloading times results in demurrage fees (born by Charterers), which courts consider as pre-set damages, not penalties (we will talk about this in more details, below, keep reading!).


On the other hand, completing vargo operations earlier than agreed, can earn charterers a "despatch" reward. This incentive is common in dry cargo contracts, where quicker turnarounds benefit all parties. Whether you're a ship owner or charterer, mastering these terms ensures smoother negotiations and fewer disputes.


Key Takeaways

  • Laytime refers to the designated period for loading and unloading cargo as specified in a charterparty agreement.

  • Demurrage is the payment made by the charterer to the shipowner for surpassing the laytime.

  • Despatch money is a reward given to the charterer for completing cargo operations efficiently within laytime.

  • Grasping these concepts is essential for effective cost management in maritime chartering.

  • Shipowners and charterers need to carefully handle these terms to enhance shipping logistics.

  • Laytime begins when a valid Notice of Readiness is issued, even if cargo operations have not started.

  • Demurrage serves as liquidated damages for delays, rather than arbitrary penalties.

  • Despatch rewards incentivize efficient cargo handling in dry bulk agreements.

  • Legal precedents such as The Tres Flores influence how courts interpret charterparty terms.

  • Clear contractual language reduces risks for both shipowners and charterers.

 

Understanding Maritime Chartering Basics

Maritime chartering is a complex process, encompassing numerous shipping contracts and charterparty clauses. Grasping the fundamental concepts and maritime terms is crucial for navigating this intricate world.


A charter party is a legally binding contract between a shipowner and a charterer. It outlines the terms and conditions for the vessel's use, including vessel scheduling, cargo handling time, and other details. There are three primary types of charter parties:


Dockworkers guide a massive cargo ship adorned with a clock motif at the bow into the bustling port, under a vibrant, dusk-lit sky.
Dockworkers guide a massive cargo ship adorned with a clock motif at the bow into the bustling port, under a vibrant, dusk-lit sky.

Definition of Charter Party

A charter party is a contractual agreement between a shipowner and a charterer. It outlines the terms and conditions for the vessel's use. The contract specifies the charter type, duration, cargo, and responsibilities of both parties. Charter parties are vital in the maritime industry, providing a clear framework for the efficient and safe transportation of goods by sea.


Laytime, Laydays and Laycan

In maritime chartering, understanding laytime, laydays, and laycan is paramount. These terms define the loading and unloading timeframes and the vessel's arrival window at the port.


A bustling seaport scene captures the dynamic movement of cargo ships and containers, highlighting international trade. The presence of a giant clock in the sky adds a surreal touch to the busy harbor, symbolizing the timeless nature of global commerce.
A bustling seaport scene captures the dynamic movement of cargo ships and containers, highlighting international trade. The presence of a giant clock in the sky adds a surreal touch to the busy harbor, symbolizing the timeless nature of global commerce.

Definition of Laytime

Laytime is a critical component in maritime shipping, representing the specific period allocated for the handling of cargo as has been pre-agreed in the charter agreement between the shipowner and the charterer. This period is crucial for ensuring that the logistics of loading and unloading cargo are conducted efficiently. Laytime commences when the vessel arrives at the designated port and submits a valid notice of readiness (NOR).


The NOR is an essential document that signifies the ship's readiness to load or discharge cargo, and it must meet specific requirements to be considered valid. This include amongst others:

  • the ship being in a safe berth (or in port vicinity, whatever is pre-agreed in the charter party),

  • having the necessary equipment, and

  • being free from any impediments that could delay operations.


The precise moment the NOR is accepted marks the official start of laytime, which can significantly impact the overall shipping schedule and costs.


Definition of Laydays

Laydays, on the other hand, refer to the specific timeframe, measured in days, during which a vessel is expected to arrive at the loading port and submit a valid NOR. This period is predetermined in the charter party and is crucial for both parties involved. The laydays set expectations for the shipowner regarding when they should have their vessel at the port and ready for cargo operations, while also providing the charterer with a timeframe within which they can plan their logistics and supply chain management. If the vessel arrives outside of these laydays, it can result in various penalties or renegotiations, affecting the overall cost and efficiency of the shipping process.


Understanding Timing in Maritime Trade: Demurrage, Laytime, and Despatch Explained Through Imagery of Shipping and Clock.

Definition of Laycan

Laydays and Laycan are terms used in maritime chartering that are related but not interchangeable. Laycan (Lay Cancelling) refers to the deadline by which the vessel must present a valid NOR. For instance, if the Laycan is set as "10/20th June," the vessel must arrive no earlier than June 10th and no later than June 20th. If the vessel arrives after June 20th, the Charterers have the right to "cancel" the charter agreement. Although actual cancellation is rare and considered a drastic measure, it often provides Charterers with leverage and negotiating power to impose penalties or negotiate more favorable terms with ship owners.


Notice of Readiness and Its Role

The notice of readiness (NOR) is pivotal, marking the vessel's arrival and readiness for cargo operations. For a NOR to be valid, the vessel must be at the designated location and fully prepared. The NOR initiates laytime, and any delays beyond the agreed time can incur demurrage charges on the charterer.


Methods for Calculating Laytime

Laytime calculation methods vary, based on the charter agreement. Common approaches include:

  • Running days: Laytime is counted continuously, including weekends and holidays.

  • Weather working days: Laytime pauses during adverse weather preventing cargo operations.

  • Sundays and holidays excepted (SHEX): Laytime pauses on Sundays and holidays.


The selected method significantly influences cargo operation duration and potential demurrage or despatch.


Reversible vs. Non-Reversible Laytime Concepts

Reversible laytime allows unused loading time at the loading port to be transferred to the discharging port. In contrast, non-reversible laytime treats each port separately, with specific time allocations for loading and discharging that cannot be transferred.


A dynamic port scene depicting efficient logistics, with a container ship being loaded as a worker monitors real-time performance data on a tablet and a stopwatch tracks progress.

This can lead to increased costs and logistical challenges if delays occur, as there is no buffer between ports. The choice between reversible and non-reversible laytime depends on factors like cargo type, port conditions, and contract terms. Perishable or time-sensitive cargo may favor reversible laytime, while efficient ports may suit non-reversible laytime. The decision also reflects the negotiating power of the parties involved, with shipowners preferring non-reversible laytime for stricter schedules and charterers favoring reversible laytime for flexibility. Ultimately, this decision requires strategic consideration of operational and contractual factors in maritime trade.


Demurrage: When Laytime is Exceeded

When a vessel's laytime is exceeded, the charterer may incur demurrage charges. Demurrage is a fee paid by the charterer to the shipowner for the additional time the vessel spends in port, beyond the agreed laytime.


It is crucial for charterers to understand the causes of demurrage and how to avoid these expenses through careful planning and thorough documentation.


Common Causes of Delays

Several elements can cause delays in cargo operations (attributable to Charterers, not Ship Owners), leading to demurrage charges. These include:

  • Port congestion and limited berth availability

  • Adverse weather conditions during loading/unloading

  • Customs clearance issues

  • Cargo documentation discrepancies

  • Port/terminal equipment breakdowns


Documenting and Claiming Demurrage

To successfully claim demurrage, ship owners must present precise documentation of port operations (i.e a timesheet of operations). This documentation encompasses:

Document

Purpose

Notice of Readiness (NOR)

Indicates the vessel's arrival and readiness to load/discharge cargo

Statement of Facts (SOF)

Records the time spent on each activity during the port stay

Time Sheets

Detailed logs of the vessel's activities, signed by the master and terminal representative

Pumping Logs

Records the time spent pumping cargo during loading/discharging operations


Required Documentation for Claims

Ship Owners must submit demurrage claims within the time limits outlined in the charter party, known as demurrage time bars. Failure to do so within these time bars can forfeit the ship owners' right to claim demurrage. The accuracy and timeliness of documentation are paramount for successful demurrage claims and to avoid disputes with Charterers.


A massive container ship, filled with colorful shipping containers, is docked at a bustling port under a clear blue sky. Cranes and various vehicles are visible on the docks, actively facilitating the process of loading and unloading cargo.
A massive container ship, filled with colorful shipping containers, is docked at a bustling port under a clear blue sky. Cranes and various vehicles are visible on the docks, actively facilitating the process of loading and unloading cargo.

Despatch: Rewarding Efficient Cargo Operations

Despatch is a financial incentive given by the shipowner to the charterer for completing cargo operations before the agreed laytime. This reward motivates charterers to optimize their port operations, provide faster loading/unloading operations & streamline the entire process. It benefits both parties in the charter agreement (i.e ship owners save time & can depart earlier for their next voyage, while charterers save money).


When Despatch Applies

Despatch is applicable under the following conditions:

  • The charterer completes cargo operations before the agreed laytime expires

  • The charterer has fulfilled all necessary documentation and customs requirements

  • No delays are attributable to the charterer or their agents


Methods of Calculating Despatch Rates

Despatch rates are usually calculated as a percentage of the demurrage rate. As a general rule of thumb, despatch is commonly at half the rate of the demurrage. For instance, if the demurrage rate is $10,000 per day, the despatch rate would be $5,000 per day. The exact despatch calculation may differ based on the charter party terms.


The despatch calculation is predicated on the time saved during the loading or unloading process. For example, if the agreed laytime is 3 days and the charterer completes the operation in 2 days, they are entitled to 1 day of despatch. This saved time equates to a financial reward for the charterer, while also benefiting the shipowner by enabling the vessel to commence her next voyage sooner.


Demurrage Rate (per day)

Despatch Rate (per day)

$10,000

$5,000

$15,000

$7,500

$20,000

$10,000


Practical Implications for Shipowners and Charterers

The concepts of laytime, demurrage, and despatch hold substantial implications for both shipowners and charterers in the maritime sector. To enhance voyage performance and reduce risks, both entities must adopt effective strategies and follow shipping best practices. Grasping the subtleties of these terms and their practical applications enables shipowners and charterers to reduce disputes and cultivate successful partnerships.


Risk Mitigation Strategies for Owners

Shipowners can mitigate risks related to laytime and demurrage by:

  • Drafting charterparty clauses with precision to clearly outline laytime, demurrage, and despatch terms

  • Keeping meticulous records of vessel operations and port activities

  • Issuing notices of readiness and other pertinent documents always on-time & without delay

  • Engaging in regular dialogue with charterers to address potential delays or issues


Risk Mitigation Strategies for Charterers

Charterers can minimize their exposure to demurrage claims by:

  1. Engaging in comprehensive pre-fixture voyage planning to ensure efficient cargo operations

  2. Monitoring port activities and vessel progress closely to identify and address delays

  3. Keeping open lines of communication with shipowners and port authorities

  4. Providing necessary documentation and instructions promptly to facilitate smooth operations


A group of workers gathers at a bustling port, where a large cargo ship is being loaded with colorful containers. Cranes loom in the background under a cloudy sky. An overlay of a clock and hourglass symbolizes the urgency and precision required in global shipping logistics.
A group of workers gathers at a bustling port, where a large cargo ship is being loaded with colorful containers. Cranes loom in the background under a cloudy sky. An overlay of a clock and hourglass symbolizes the urgency and precision required in global shipping logistics.

When disputes arise concerning demurrage claims or other chartering matters, it is essential for both shipowners and charterers to focus on maintaining clear documentation and resolving issues promptly. This is where post-fixing becomes significant. Efficient post-fixing can reduce disputes, enhance communication, and decrease the likelihood of arbitration. Effective mechanisms for resolving maritime disputes are vital. By proactively tackling potential challenges and adopting a cooperative approach, both parties can enhance their chartering strategies and cultivate mutually beneficial relationships within the shipping industry.


FAQ

What is the difference between a voyage charter and a time charter?

In a voyage charter, the shipowner bears all operational expenses. The charterer, on the other hand, covers the cargo's transportation costs from one port to another. A time charter, by contrast, involves the charterer hiring the vessel for a set period. They are responsible for fuel and port charges. The shipowner manages the crew and maintains the vessel.


How is laytime calculated?

Laytime calculation employs various methods, such as running days or weather working days. The chosen method is agreed upon in the charterparty. It considers weather, port operations, and exceptions.


What is the difference between reversible and non-reversible laytime?

Reversible laytime allows unused time at the loading port to be applied to the discharging port. This provides the charterer with extra time for cargo operations. Non-reversible laytime, by contrast, treats loading and discharging ports separately, without transferring unused time.


What documentation is required when submitting a demurrage claim?

To submit a valid demurrage claim, essential documentation includes the Notice of Readiness (NOR) and a statement of facts. Time logs and pumping logs are also required. These documents must evidence the delay and its causes.


How is despatch calculated?

Despatch is calculated at half the demurrage rate and is paid by the shipowner to the charterer for time saved. The despatch rate and conditions are specified in the charterparty.


What are some common causes of demurrage?

Demurrage is often caused by port congestion, adverse weather, and cargo availability issues. Customs delays and inefficient cargo handling also contribute to delays, leading to demurrage charges.

Kommentare


Address

Posthoornstraat 17

3011WD, Rotterdam

Netherlands

KvK: 90841026
VAT: NL004846091B43

Contact

0031 (0) 85 00 45451

© All rights reserved. Virtue Marine

 

bottom of page